Adani Group Discussed Hydropower Projects in Uzbekistan
The potential 5-gigawatt investment would mark a significant international expansion of the firm's energy storage infrastructure.
Updated on Sept. 21, 2026 in Utilities

Live Poll
Do you believe international corporate energy partnerships improve a nation's energy security?
Adani Group met with Uzbekistan government officials in August 2026 to discuss the development of four pumped-storage hydropower projects. The proposed infrastructure expansion targets an indicative investment of ₹30,000 crore to help the nation reach its renewable energy goals.
Why it matters
Uzbekistan seeks to stabilize its grid and hit a 50% renewable energy share by 2030, creating a massive opportunity for developers to provide energy storage. For operators, this move signals a broader shift in regional energy markets as nations look to private capital for grid-balancing solutions.
The proposed project involves 5 gigawatts of capacity, compared to Uzbekistan's current total hydropower base of 2.5 gigawatts. The initiative carries an indicative investment value of ₹30,000 crore, calculated using a benchmark cost of ₹6 crore per megawatt.
The players
Adani Group
A multinational conglomerate with significant market positioning in infrastructure, ports, and energy storage development.
Narendra Modi
The Prime Minister of India who maintains diplomatic and economic ties with Central Asian leadership.
The details
Pumped-storage systems function as grid-scale batteries by moving water to an upper reservoir during low-demand periods and releasing it through turbines during peak usage. Adani Group is leveraging its existing experience with 3 gigawatts of pumped-storage capacity in India to pursue this project. Should the deal proceed, Uzbekistan would become the first Central Asian nation to implement such utility-scale storage technology.
Timeline
May 2026: Uzbekistan adopted a presidential resolution for pumped-storage projects.
August 2026: Adani Group held talks with Uzbekistan officials.
August 10, 2026: UZDAILY reported on the proposed hydropower projects.
August 29-30, 2026: Prime Minister Narendra Modi visited Uzbekistan.
2032: Deadline for completing three large pumped-storage projects.
Market Landscape
The potential investment follows Uzbekistan's May 2026 presidential resolution, which mandates the development of three large pumped-storage projects by 2032. This aligns with a broader trend in Central Asia of courting international infrastructure expertise to meet aggressive 2030 renewable targets.
Operators in the energy sector should monitor how Uzbekistan manages the tender and execution of these projects as a bellwether for foreign investment in Central Asian power infrastructure. The transition toward 50% renewable reliance by 2030 suggests increasing demand for specialized grid-balancing technology.
The takeaway
The move underscores the growing role of international developers in scaling grid-stability solutions in emerging markets. Operators should track the 2032 completion milestone for these projects as a potential indicator of successful regulatory and technical integration.
Further reading
For broader trends in infrastructure and sector-specific shifts, see our coverage of Utilities.
Source note: This article includes information reported by Mint.